If the launch date is fixed, define the deliverables first: scenes, duration, aspect ratios and approval owners. Two films of the same length may require very different production and review effort.

Logistics, generation attempts, accuracy checks and approvals have different weights on each project. Choosing a method means identifying which stages can actually become shorter.

Where the time goes in traditional production

In a commercial's schedule, the real time is not spent shooting. The shoot is usually one or two days. Time is spent making the shoot possible.

StageWhat happensWhat extends it
Concept and scriptIdea, storyboard, pitchApproval rounds
CastingAgency calls, auditions, dealsAvailability of the right profile
LocationScouting, permits, contractsPermit processes, season, weather
Pre-productionCrew, equipment, transport, insuranceCalendar conflicts
ShootThe set dayWeather, incidents, reshoots
Post-productionEdit, grade, sound, effectsRevision rounds

Casting and location preparation may be reduced in some fully digital projects. Actual product photography, an actor performance or hybrid scenes keep those stages in the schedule.

Build the timeline around the chosen method and the agreed deliverables.

Where the time goes in AI production

A plan for El Chedo AI Studio in Antalya can be organised into four areas. They do not impose a standard duration on every project; review and approval needs shape the schedule.

01

Concept and visual direction

Narrative, tone, reference world and framing logic are set. The decisions here steer the whole production, so they are not rushed. This is the most valuable part of the schedule.

02

Identity and preparation

Prepare references for product or face accuracy and consider custom training where useful. Check that an existing system suits the new brief. Training is not mandatory for every job.

03

Generation

Generate key images, motion attempts and variations. Some work can run in parallel; selecting and correcting unsuccessful outputs still requires human time.

04

Edit and final pass

Edit, sound, grade and retouch. This stage is no different from traditional production, because this part of the work is still craft.

The new bottleneck: the approval loop

Both physical shoots and AI production can require script, visual direction, first-cut and final approvals. Agreeing a variation limit and consolidating feedback helps reduce repeat work.

An inversion results: as production speeds up, the project slows down because of a team that will not decide.

What actually determines the schedule

FactorEffect
Whether an identity system already exists for the brandPreparation may shorten if an existing system suits the new product and quality standard; validation and any updates still need time.
Product complexityFlat, simple products are fast. Multi-part, reflective, fine-text products are slow.
Whether people appearFaces and hands extend the control stage. Product-led work moves faster.
Number of languages and formatsReplication from one production is where AI is strongest, at very low marginal cost.
Number of approval roundsThe real cause of most delays. It comes from the decision process, not production.
Whether the job is hybridWork combined with live shooting reintroduces a shooting schedule.

What speed solves, and what it does not

Fast experiments can reveal creative options early. Physical production also offers preparation and pickup options; AI attempts remain limited by costs, tool limits and review capacity.

  • Fully digital environments may reduce some location and travel requirements.
  • Language and framing versions can reuse shared production; every version needs review.
  • Alternative directions can be explored before final production decisions.
  • A good concept, accurate product representation and consistent motion still require work.
  • Hybrid scenes remain affected by weather, set and team availability.
  • Catalogue work requiring actual product photography needs that source to be prepared.

Speed is not an outcome, it is an option. What is valuable is not fast delivery but being able to afford more than one attempt.

How the schedule becomes real

A realistic schedule can only be given once scope is settled. Proposals from El Chedo AI Studio in Antalya carry a schedule once three things are known: how many key frames or seconds of video, how many languages and formats, and how many approval rounds.

Any duration quoted before those three are defined is a guess. Schedules built on guesses do not hold.

Three illustrative delivery schedules

Stage / working daysA: 1 scene, 6 secondsB: 3 scenes, 15 secondsC: 5 scenes, 30 seconds
Brief and preparation123
Key image and direction approval123
Motion generation and review124
Edit, sound and versions123
Final review and delivery112
Illustrative total5 working days9 working days15 working days

A assumes ready references and one frame format; B a short film in two formats; C more scenes, sound and adaptations. Actual product shooting or training calls for a revised plan. Use the brief template with the quote comparison to define the scope.